Ophthalmic refurb & oncology new build for Kingston Hospital

Location: Kingston upon Thames, Surrey

Client: Kingston Hospital NHS Foundation Trust

Value: £700,000

Contract type: Nominated subcontractor to Storm Building Ltd for refurbishment and extension project

Overview

Working with services consultant Bianco Sale, Barton Knight Contracting was nominated by its long-term principal contractor partner, Storm Building, to install the electrical works for a refurbishment and new build extension of the Royal Eye Unit at Kingston Hospital in this 2-phase project.

The 3-storey extension includes a new Paediatric Oncology ward on the second floor, and a plant room on the top floor.

Key Works

Electrical works comprised:

  • New switchgear
  • New metering
  • Bedhead trunking
  • A nurse call system
  • New lighting and power supplies plus containment.
  • An extension to the fire alarm was included as well as data cabling and air conditioning units.
“Barton Knight Contracting has done a very good job on the REUPO project at Kingston hospital. I would not hesitate in using them again and recommending them. They have undertaken their works professionally and to a good standard – with minimal issues – on a difficult project. Effective communication and co-ordination have been good from the very first day. Credit to the site installation and management team."
Site Management Team, Storm Building Ltd
barton knight accreditations

Phase 1 of this 2-stage electrical project was to extend the existing eye casualty department in the Royal Eye Clinic at Kingston Hospital. A 3-storey extension was built in the six months from June 2023, to enlarge and refurbish the ophthalmology department on the ground floor, and add a Paediatric Oncology ward on the second floor, plus a plant room on the 3rd floor.

Phase 2 of the project is already under-way and focuses on a smaller area within the new build, but is confined to the ground floor/Level 2, comprising consultation rooms and vision lanes. With Phase 1 completed in December 2023, the ophthalmics on the refurbished and extended ground floor (called Level 2, as there is an undercroft area underneath) now comprise retinol consultation rooms, examination rooms, injection rooms, imaging rooms, vision rooms, circulation and support units. Waiting areas, nurse rooms and children’s play area are also part of this floor.


The Paediatric Oncology department includes chemotherapy preparation rooms, patient cubicles and bays, and support areas.


The electrical works included new switchgear, metering, bedhead trunking and nurse call system, as well as a fire alarm system extension, data cabling and containment. The area was blocked off from the main hospital (to minimise the noise and dust of construction work), which meant that work was completed in normal working hours, although some extra weekends were included to ensure the job was completed to schedule.

For every large NHS electrical project Barton Knight Contracting appoints a dedicated onsite foreman to ensure the day-to-day running of the works go smoothly and any obstacles are overcome.

Electrical Site Supervisor Scott Ferguson explains how some of the issues on the Kingston project were dealt with:

“We had some problems with getting the mains supply into our new panel to feed the extension. The route advised was too congested with existing services, so working closely with Storm Building and Bianco Sale, we advised that the route be moved externally on ladder containment. We also altered the cable from an 185mm 4 Core to Parallel 95mm 4 core SWA cables. These amendments allowed us to complete the power-supply stage efficiently and quickly.”

In addition, during the ground works, asbestos was found in the soil. This caused some delays, but Barton Knight Contracting was able to keep to the tight schedule required by using a larger team to run several parts of the works at once.


“The project was still completed on time and to the high standard we pride ourselves on,” adds Scott.

Why work with Barton Knight Contracting?

Significant experience in complex NHS work

Electrical, fire, access system and associated civil engineering work coordinated centrally

All employees H&S certified + Advanced CRB Checks

Dedicated project manager - ensures quick decisions to keep your project on schedule

Detailed quotations with site visits for in- depth project knowledge

Onsite foreman - for good collaboration and communication with all parties

Recommended by previous clients – ask us for details

Our Projects

New Generators and Panels for St Peter’s Hospital

12-month project

Hillingdon Hospital ICU Conversion

14-week electrical project

Elective Procedure Rooms for New QEII Hospital

16-week project

Ophthalmic refurb & oncology new build for Kingston Hospital

6-month project

Resilience for St Peter’s Hospital

6-month project

New generator panel for Wexham Park

2-phase project over 11 months