Infrastructure upgrade for Newham Hospital

Location: Plaistow, East London

Client: Barts Health NHS Trust

Value: £2.5 million

Contract type: Design and installation

Overview

This electrical infrastructure project for Newham University Hospital focused on upgrading the
transformers and panels to support the estate with reliable power and better resilience. The new
equipment includes additional safety features which make it easier to maintain, too.

Barton Knight Contracting worked with the Capital Projects team, consultants E-Sine, principal
designers Playe & Partners LLP, and contract administrator Castons.

Key Works

Upgrade of:
• 2x 1600kVA transformers, replacing 2x 800kVA transformers
• 2x 2500amp ‘Form 4’ LV panels, replacing 2x 1600amp panels
• 3x individual 500mm AWA cabling per phase
• Outgoing cabling from 10mm 2-core to 400mm 4-core SWA

Using an experienced and trusted team is essential when you’re working in a live environment and the hospital has to keep running. Our electricians have worked on many similar healthcare contracts so there were no issues on this project."
Simon Holder, Barton Knight Project Manager
barton knight accreditations

Our electrical infrastructure project for Newham University
Hospital, part of Barts Health NHS Trust, focused on
replacing and upgrading outdated equipment for extra
capacity and resilience, futureproofing the site and allowing
for easier maintenance
.


The electrical works are part of a broader net-zero and
energy efficiency programme
, aiming to reduce carbon
emissions, save money on energy bills, and ensure the
reliability and security of electrical supply.


We replaced and upgraded two 800kVA transformers
with two 1600kVA transformers – essentially doubling the
power capacity for the estate
– migrating across existing
High Voltage (HV) cabling.


Two Low Voltage (LV) 2500amp panels were built and
installed to replace the existing 1600amp panels.

The cables from the transformer powering the panel were three
individual 500mm AWA (Aluminium Wire Armour) per phase.
From the LV panels to the hospital areas more robust SWA
(Steel Wire Armour) cabling was specified, varying from
10mm 2-core to three 400mm 4-core cables.


The LV panels were installed and commissioned one at a
time to ensure the hospital was able to continue running as
normal. The new panels are ‘Form 4’ and have the highest
level of internal separation, ensuring maximum safety and
isolation of live parts.


This means if there is an electrical problem (eg short circuit,
overload etc) you can separate the faulty section and
work on it without having to isolate the whole panel. The
panels therefore are more robust and reliable and allow for
smoother power distribution, as well as easier installation
and maintenance.


“The new infrastructure supports the entire NHS side of
the hospital,” explains Simon Holder, Electrical Project
Manager for Barton Knight Contracting
. “There is a separate
section of the estate – the Barts Health London Private
Care centre
– which is not NHS and has its own equipment,
although there was some cross-over to be managed.”

This multi-phase project started in 2023 and was
successfully delivered to budget in April 2025, with all
transformers and panels live

Why work with Barton Knight Contracting?

Significant experience in complex NHS work

Electrical, fire, access system and associated civil engineering work coordinated centrally

All employees H&S certified + Advanced CRB Checks

Dedicated project manager - ensures quick decisions to keep your project on schedule

Detailed quotations with site visits for in- depth project knowledge

Onsite foreman - for good collaboration and communication with all parties

Recommended by previous clients – ask us for details

Our Projects

Infrastructure upgrade for Newham Hospital

2.5 years

New Generators and Panels for St Peter’s Hospital

12-month project

Hillingdon Hospital ICU Conversion

14-week electrical project

Elective Procedure Rooms for New QEII Hospital

16-week project

Ophthalmic refurb & oncology new build for Kingston Hospital

6-month project

Resilience for St Peter’s Hospital

6-month project