New generator panel for Wexham Park

Location: Slough

Client: Wexham Park Hospital (NHS Frimley Health Foundation Trust)

Value: £1.2 million

Contract type: Principal contractor, working with external consultants Stuart McCurry & Partners

Overview

A generator changeover panel was fitted along with other works in June 2022, during the first phase of this project. It was designed to run in conjunction with the existing pharmacy switchboard and provide back-up support in the event of a mains power failure.

In Phase 2, a 1400kVA generator was installed in a difficult-to-access courtyard, lifted in via a 1,000-tonne crane set up in a car park 55 metres away. This was completed in just 18 hours.

Key Works

  • Installation of a 2,000amp generator changeover panel fitted with a set of Castell Keys
  • Exterior 2,000amp VEAM connection unit, installed for additional resilience
  • Switch room extension built to allow room for generator panel
  • Demolition work, design and build of custom concrete base
  • Installation of 26-tonne 1400kVA generator
Barton Knight Contracting is a known force for good at Wexham Park and a trusted supplier, having undertaken very complex and sensitive works over many years for the Trust "
Geoff Irish, Senior Project Manager, Wexham Park Hospital
barton knight accreditations

In this dual-phased project, Barton Knight Contracting was engaged directly by Wexham Park Hospital to provide additional power and resilience for the pharmacy area, comprising kitchens, wards, IT and critical care units.


In the initial phase, which started in June 2022, a 2000amp generator changeover panel fitted with a set of Castell Keys was installed. This was designed to run in conjunction with the new pharmacy panel and provide back-up support in the event of a mains power failure.


An extension to the switch room was also built, adding an extra 10 square footage to allow room for the new generator.


An additional 2000amp VEAM connection unit in stainless steel (and therefore weatherproof) was installed outside for additional resilience. Finally, Barton Knight upgraded the LV (Low Voltage)
transformer to HV (High Voltage) to increase the load available and allow for future provision.


The second stage – supplying and fitting a 1400kVA generator – was completed in July 2023. The new generator was commissioned to provide further resilience to the pharmacy area and installed in a small courtyard.


Some small existing buildings were demolished first and then a new concrete base was laid – specifically designed for the 26-tonne generator and its fuel tank.


The courtyard was adjacent to a mortuary which required constant access, so Barton Knight had to adjust the works accordingly while minimising disruption to this critical live environment.


As the courtyard was surrounded on all sides, the generator had to be lifted in by a 1,000-tonne crane (assembled by a smaller, 200-tonne crane), set up in a car park 55 metres away. Once in place, 16 500mm Aluminium Wire Armoured (AWA) cables were run from the switch panel to power the generator.


The lifting and installation were completed in 18 hours, as the car park could only be closed for one day.

Why work with Barton Knight Contracting?

Significant experience in complex NHS work

Electrical, fire, access system and associated civil engineering work coordinated centrally

All employees H&S certified + Advanced CRB Checks

Dedicated project manager - ensures quick decisions to keep your project on schedule

Detailed quotations with site visits for in- depth project knowledge

Onsite foreman - for good collaboration and communication with all parties

Recommended by previous clients – ask us for details

Our Projects

New Generators and Panels for St Peter’s Hospital

12-month project

Hillingdon Hospital ICU Conversion

14-week electrical project

Elective Procedure Rooms for New QEII Hospital

16-week project

Ophthalmic refurb & oncology new build for Kingston Hospital

6-month project

Resilience for St Peter’s Hospital

6-month project

New generator panel for Wexham Park

2-phase project over 11 months