New ICU for St Peter’s Hospital

Location: Surrey

Client: St Peter's Hospital

Value: £300,000

Contract type: Subcontracted to Rex Hurst & Sons Ltd for electrical power supply, UPS and ACU installation.

Overview

Speed of response and delivery in this 8-week project was critical. Barton Knight Contracting delivered the design and installation of electrical power and lighting supply to a new 12-bed ICU ward at St Peter’s Hospital, designed specifically for Coronavirus patients.

Working with main contractor, Rex Hurst Ltd, Barton Knight successfully delivered the project delivered at the height of the pandemic in Autumn 2020.

Key Works

Lights and power to the new COVID-19 critical care ward. Bedhead trunking for 12 new beds, installation of a new UPS system, temporary back-up generator, and an air conditioning unit.

The ACU was a standalone unit, designed to filter out the virus, and work separately to the ventilation system for the main hospital.

"Barton Knight Contracting was able to quote for and deliver this urgent project quickly and effectively. The company’s highly trained, experienced electricians were a ‘safe pair of hands'"
Stephen Hurst, Rex Hurst & Sons Ltd
barton knight accreditations

Barton Knight Contracting was approached by St Peter’s Hospital in late September 2020 to provide electrical works for a new 12-bed Intensive Care Unit (ICU) designed specifically for COVID-19 patients – Chestnut Ward. The design and installation of a standalone air conditioning unit was also required. The unit had to filter out air potentially contaminated by the virus, and operate separately to the existing air conditioning system.

Work took place during the height of the Covid-19 pandemic, so the hospital needed a contractor that had safe, established sanitation and social distancing practices in place, but had the experience to deliver the project in eight weeks.

Barton Knight was able to deliver on all counts. As the building was already used to house COVID-19 patients, the area had to be deep-cleaned with sanitiser ‘bombs’ to ensure electrical engineers did not contract the virus. Full PPE was used by engineers, and the work progressed with minimum disruption
to staff and patients.

As St Peter’s Hospital does not have a back-up generator farm, an Uninterruptible Power Supply (UPS) had to be fitted to ensure continuous support for at least 3 hours in the event of a power cut or dip in supply. The UPS was fed into the wards via bedhead trunking which would allow the critical care machinery to operate through a power failure. Normally the UPS would only operate for a few minutes (providing power if it senses a failure of 0.02 seconds, classified as ‘unacceptable downtime’) before a back-up generator kicks in.

However, once the UPS unit was installed there was no room for the existing generator. Chestnut Ward is a modular building, and part of the ward was always designed to house intensive care units, but there wasn’t space for the new beds and the UPS unit. Barton Knight therefore installed a generator in the car park as a temporary solution.

The project was delivered on time and to budget. Barton Knight has since been contracted for further projects at St Peter’s Hospital.

Why work with Barton Knight Contracting?

Significant experience in complex NHS work

Electrical, fire, access system and associated civil engineering work coordinated centrally

All employees H&S certified + Advanced CRB Checks

Dedicated project manager - ensures quick decisions to keep your project on schedule

Detailed quotations with site visits for in- depth project knowledge

Onsite foreman - for good collaboration and communication with all parties

Recommended by previous clients – ask us for details

Our Projects

New Generators and Panels for St Peter’s Hospital

12-month project

Hillingdon Hospital ICU Conversion

14-week electrical project

Elective Procedure Rooms for New QEII Hospital

16-week project

Ophthalmic refurb & oncology new build for Kingston Hospital

6-month project

Resilience for St Peter’s Hospital

6-month project

New generator panel for Wexham Park

2-phase project over 11 months