NICU generator upgrade for St Peter’s Hospital

Location: Surrey

Client: St Peter’s Hospital

Value: £650,000

Contract type: Complete design-installation scheme for generator power upgrade for Neonatal Intensive Care Unit.

Overview

Barton Knight was awarded a £7 million, 3-year generator farm project for St Peter’s Hospital, Surrey, then deferred for a year. After a power outage at the NICU where the ward lost power for 2½ hours, Barton Knight accelerated one part of the scheme, to design and fit UPS systems to NICU.

This multi-phase project was completed at the height of the COVID-19 pandemic in 2020-2021.

Key Works

  • UPS systems fitted to the roof of the 5-storey building to supply 3h power in case of failure – as the unit was too large to fit in the Abbey Wing
  • Steel structure and GRP enclosure custom-built to house the unit, with retaining walls, handrails and trenches.
  • Scaffolding, cranes and civil works was also included, plus a base transformer on the ground floor and a supplementary panel to add capacity.
  • UKPN brought in an 11,000 volt supply to the transformer. A temporary generator has been fitted, to be replaced in the original resilience project.
“Barton Knight Contracting completed the critical electrical works safely and effectively in a live hospital environment, despite additional complications from the coronavirus pandemic.”
Sandeep Sooteehall, Capital Projects Programme Manager, Ashford & St Peter’s Hospital
barton knight accreditations

St Peter’s Hospital, Chertsey is spread over a large site, and many of the properties are over 20 years old. In 2019, the NHS Foundation Trust had decided to install a generator farm to support the hospital.

Barton Knight Contracting successfully tendered for this 3-year, £7 million scheme in April 2020, but the
contract was deferred for a year.

In September 2020 there was a power outage at the Neonatal Intensive Care Unit (NICU) in the Abbey Wing. The NICU lost all power (barring one small area) for around two and a half hours. After the power outage, the requirement to upgrade the Abbey Wing was accelerated. Barton Knight was asked to put a scheme together for the NICU based on the government’s Health Technical Memorandum 06-01 (HTM 06).

The guidance specifies all intensive care units should have three hours of continuous power available in the event of a power failure.


The Uninterruptible Power Supply (UPS) systems were too large to fit in the Abbey Wing, where the NICU was situated. So, Barton Knight designed a custom-built steel structure on the roof with a Glass Reinforced Plastic/fibreglass enclosure to house the UPS. The systems were installed via cranes, and retaining walls with handrails and trenches built around the units.

The final phase, completed in September 2021, includes civil work on the ground floor – one of the bases will house a new transformer providing power to Abbey Wing for NICU. The other base is a supplementary panel for an existing one, which had no capacity to support the IPS units.

In July 2021, the UK Power Network brought in a 11,000 volt supply to the transformer, installed by Barton Knight. A temporary generator has also been fitted to support Abbey Wing, which will eventually be replaced by the generator farm, part of the original resilience project for the entire hospital.

Barton Knight was able to provide a complete package from initial design to completion, including electrical installation, scaffolding, roofing and other building materials and works.

Why work with Barton Knight Contracting?

Significant experience in complex NHS work

Electrical, fire, access system and associated civil engineering work coordinated centrally

All employees H&S certified + Advanced CRB Checks

Dedicated project manager - ensures quick decisions to keep your project on schedule

Detailed quotations with site visits for in- depth project knowledge

Onsite foreman - for good collaboration and communication with all parties

Recommended by previous clients – ask us for details

Our Projects

New Generators and Panels for St Peter’s Hospital

12-month project

Hillingdon Hospital ICU Conversion

14-week electrical project

Elective Procedure Rooms for New QEII Hospital

16-week project

Ophthalmic refurb & oncology new build for Kingston Hospital

6-month project

Resilience for St Peter’s Hospital

6-month project

New generator panel for Wexham Park

2-phase project over 11 months