Resilience for St Peter’s Hospital

Location: Surrey

Client: St Peter’s Hospital

Value: £1.5 million

Contract type: Barton Knight Contracting was the principal contractor, working with design consultants Ridge and Partners LLP

Overview

This construction project is part of a multi-phase, £6 million programme of electrical resilience planned over several years, which Barton Knight Contracting has been working on for St Peter’s Hospital.

Comprising ground and infrastructure preparation for future generators, as well as complex civil engineering aspects, much of the work was undertaken in the worst of the winter weather, in temperatures of down to -10°C. The site is next to acute wards, so noise had to be minimised.

Key Works

  • A 500sqm concrete base was laid on a brownfield site, with infrastructure installed for a new generator farm
  • 6 metre piling fitted using the silent Giken Supercrush method
  • Main drains diverted as part of enabling works and a new storm water drain created
  • Containment for future supplies from the generator farm installed to power various switchboards when installed later in 2023
Our extensive experience in resilience projects for the NHS meant we understand the issues at stake when working in live environments, and are able to manage our employees, subcontractors and liaise with hospital staff to ensure contracts are completed with minimum disruption, and as quickly and efficiently as possible."
Mel Horton, Senior Contracts Manager, Barton Knight Contracting
barton knight accreditations

This £1.5 million civil construction project is the second stage of a larger, multi-phase £6 million programme of electrical resilience work for Ashford & St Peter’s Hospitals NHS Foundation Trust. The initial phase was a NICU critical safety equipment upgrade undertaken in 2020 and 2021, which included new Uninterruptible Power Supply (UPS), new Isolated Power Supply (IPS), a new switch panel and new sub-station.

This stage – Phase 2 – took six months. Enabling works were finished in October 2022, while the construction elements were completed in January 2023 – undertaken in winter snowstorms with temperatures of down to -10°C.

As principal contractor, Barton Knight Contracting worked on the design (with Ridge and Partners LLP) and installation of this project, fitting the electrical equipment and co-ordinating the piling installation, the drains diversion, creation of a new stormwater drain and finally, the construction of a 500sqm concrete base for two new generators.

The base was fitted on a brownfield site adjacent to the main Outpatients department and Acute wards, so noise had to be kept to a minimum to avoid disruption to patients and staff. After trees and fences etc. were cleared from the site to make it accessible, 6 metre piles were pushed into the ground using
the virtually silent Giken Supercrush method where hydraulic press-in and augering takes place simultaneously. Conventional installation uses presses and/or vibratory or impact hammers to push the piling into the ground, and is much noisier.

For safety reasons a handrail was fitted on top of the piling, while containment to carry future supplies from the generator farm (to power a number of individual switchboards) was also installed. This included fitting multiple 900mm heavy duty ladder racking systems, which were craned in over the rooftops of neighbouring buildings.

Phase 3 of the resilience programme covers the supply, installation and commission of two T1650 – 1500kVA 400v 50Hz prime rated diesel generating sets, which will be fitted at St Peter’s Hospital later in 2023.

Why work with Barton Knight Contracting?

Significant experience in complex NHS work

Electrical, fire, access system and associated civil engineering work coordinated centrally

All employees H&S certified + Advanced CRB Checks

Dedicated project manager - ensures quick decisions to keep your project on schedule

Detailed quotations with site visits for in- depth project knowledge

Onsite foreman - for good collaboration and communication with all parties

Recommended by previous clients – ask us for details

Our Projects

New Generators and Panels for St Peter’s Hospital

12-month project

Hillingdon Hospital ICU Conversion

14-week electrical project

Elective Procedure Rooms for New QEII Hospital

16-week project

Ophthalmic refurb & oncology new build for Kingston Hospital

6-month project

Resilience for St Peter’s Hospital

6-month project

New generator panel for Wexham Park

2-phase project over 11 months