Theatre refurb after fire, Ashford Hospital

Location: Surrey

Client: Ashford and St Peter’s NHS Foundation Hospital Trust

Value: £200,000

Contract type: Nominated subcontractor for electrical wiring replacement and testing after fire damage.

Overview

Emergency refurbishment work was required after a fire damaged several rooms (including an operating theatre) at Ashford Hospital in August 2021.

The hospital’s Project Manager nominated Barton Knight to the insurance company as the electrical contractor had successfully completed work on a ward previously. The work started a couple of weeks after the damage occurred and was completed in a live environment.

Key Works

New cable flow trunking for power, data and medical gases, new surgeon’s panel, surgeon’s light, and new anaesthetic light.

Additional UPS (and IPS to support it), new distribution board, replacement data and fire alarm, plus mechanical wiring

"We were happy to work with Barton Knight Contracting again on another project for Ashford & St Peter’s Hospital. Speed of response and delivery was essential. Working with Rex Hurst, Barton Knight was able to complete this job on time and to budget"
Stephen Hurst, Rex Hurst & Sons Ltd
barton knight accreditations

Barton Knight Contracting was initially contacted in August 2021 to test some wiring subjected to fire damage.


Ashford’s Project Manager, Guangmo Zhu, put Barton Knight forward as a nominated contractor to the insurer, having worked successfully with the company previously. Barton Knight had completed another job that required a rapid turnaround in 2020, working with main contractor, Rex Hurst & Sons Ltd, on an
eight-week project to provide electrical works for a new 12-bed Intensive Care Unit for COVID-19 patients.


For the new project, Barton Knight was subcontracted again to Rex Hurst for electrical power supply. Barton Knight also installed additional UPS (Uninterruptible Power Supply) and supporting IPS (Isolated Power Panels) circuits, to ensure continuous power for at least three hours in the event of a cut or dip in supply.


Work started in September, just a few weeks after the fire occurred, and was successfully completed before Christmas, just three months later. Several rooms had sustained damage after the fire, which occurred due to a faulty phone charger. The handset had been left on a trolley which had some semi-flammable packing dressing on it, which then caught fire. There was a significant amount of smoke damage – approximately £350,000 worth – and an operating theatre, anaesthetic rooms, plus a couple of ancillary rooms needed to be refurbished.


All existing wiring was removed, going right back to the cell/basic structure of the rooms, and the theatre was thoroughly cleaned before further work was undertaken. Then new cable flow trunking for power, data, and medical gases was fitted, as well as the UPS, IPS, new distribution board, replacement data and fire alarm and mechanical wiring. A new, specialist Starkstrom surgeon’s panel was installed, controlling air con, data, power and lighting in the operating theatre. Barton Knight also fitted a surgical lighthead and specialist lighting for the anaesthetist.

Barton Knight’s experienced team of electricians was able to successfully complete this urgent project quickly and effectively, with minimum disruption to staff and patients.

Why work with Barton Knight Contracting?

Significant experience in complex NHS work

Electrical, fire, access system and associated civil engineering work coordinated centrally

All employees H&S certified + Advanced CRB Checks

Dedicated project manager - ensures quick decisions to keep your project on schedule

Detailed quotations with site visits for in- depth project knowledge

Onsite foreman - for good collaboration and communication with all parties

Recommended by previous clients – ask us for details

Our Projects

New Generators and Panels for St Peter’s Hospital

12-month project

Hillingdon Hospital ICU Conversion

14-week electrical project

Elective Procedure Rooms for New QEII Hospital

16-week project

Ophthalmic refurb & oncology new build for Kingston Hospital

6-month project

Resilience for St Peter’s Hospital

6-month project

New generator panel for Wexham Park

2-phase project over 11 months