Wexham Park Hospital

Location: Slough

Client: Wexham Park Hospital (NHS Frimley Health Foundation Trust)

Value: £2.8 million

Contract type: Principal contractor for switch panel replacement in 3 wards plus cabling for generators and infrastructure for G99 unit

Overview

This project was to upgrade the panels and back-up power (under HTM 06) for maternity, psychiatric and critical care units.

The work was completed in a live environment and 3 large generators were installed on site to support the wards during the project. Barton Knight’s onsite foreman/dedicated project manager worked with department heads and matrons to reassure them that their wards could continue to operate with minimum disruption.

Key Works

Replacement of main switch panels, installation of automatic transfer switches, maintenance of existing systems while migrating cables to new system, plus infrastructure for G99 unit.

The maternity switch room panel involved the migration of over 100 sub-board distribution cables which supported 20 live wards, lifts and auxiliary areas.

Infrastructure projects often mean subcontracting half a dozen companies. It’s more costefficient and effective to employ an experienced specialist which can ‘do it all’, such as Barton Knight."
Geoff Irish, Senior Project Manager
barton knight accreditations

This project was completed in late 2019, and comprised of £1.2 million electrical works and £1.6 million for the generators.

As the project was completed in mid-winter, Barton Knight’s contractors had to work flexibly in live environments around the hospital at times deemed less critical.

The upgrade was required under the government’s Health Technical Memorandum 06-01 (HTM 06) for electrical services supply and distribution. The guidance specifies that hospitals should have three hours of continuous power available in the event of a power failure. The work completed by Barton Knight has ensured the maternity, psychiatric and critical care wards have full generator support.

In one switch room the existing switch panel was in the centre of the room, with peripheral panels around the walls – an inefficient arrangement. To complete the upgrade without compromising the electrical supply, Barton Knight had to clear one area first to fit the initial part of the new main panel, and then migrate it across over 3 months. The new feeder pillar was installed outside with a transformer to support it, in turn backed-up by a new 1,000 kVA generator in an adjacent room.

The new maternity switch room panel was too large for the room, so it was split in two and joined across the top of the doorway by a busbar.

Wexham Park also required extra electrical capacity – when the generators are running the hospital wanted the facility to transfer excess power and sell it back into the grid under the Energy Networks Association’s (ENA) G99 regulation. Barton Knight fitted the infrastructure for the UK Power Network to adopt the unit, ensuring the hospital is paid for feeding power back at peak times, offsetting the installation costs of the panels and generators.

“This arrangement is less common since National Grid lowered what it pays for electricity, but we anticipate further projects as general electricity prices rise,” comments Mel Horton, Senior Contracts Manager for Barton Knight Contracting.

Barton Knight has since been employed by Wexham Park Hospital to work on several other schemes.

Why work with Barton Knight Contracting?

Significant experience in complex NHS work

Electrical, fire, access system and associated civil engineering work coordinated centrally

All employees H&S certified + Advanced CRB Checks

Dedicated project manager - ensures quick decisions to keep your project on schedule

Detailed quotations with site visits for in- depth project knowledge

Onsite foreman - for good collaboration and communication with all parties

Recommended by previous clients – ask us for details

Our Projects

New Generators and Panels for St Peter’s Hospital

12-month project

Hillingdon Hospital ICU Conversion

14-week electrical project

Elective Procedure Rooms for New QEII Hospital

16-week project

Ophthalmic refurb & oncology new build for Kingston Hospital

6-month project

Resilience for St Peter’s Hospital

6-month project

New generator panel for Wexham Park

2-phase project over 11 months